Big Gun enlisted to deliver Conway rocket

Following representations from LVIG and Ladywell traders, Mayor Sir Steve Bullock will on Friday meet representatives of the Ladywell business community - and has invited contractor Conway to attend.  In its recent letter to the Mayor, LVIG Chairman Tony Rich wrote:
" . . . the Ladywell Village Improvement Group has fought hard for, and is strongly supportive of, the Ladywell public realm improvements currently underway . . . We write to you now, however, because we've been notified of further major slippage on the scheme - in particular that Ladywell Road is unlikely to be reopened until the end of October.  This significantly prolongs the disruption to local businesses, residents and others for whom Ladywell Road is the obvious route to work.  Whilst the scheme has experienced some unforeseen disruption I do feel that some of the delays could have been anticipated, obviated and/or minimised by better management of the contract, and the application of greater pressure on Conways to adhere to agreed timescales and to bring in more staff as necessary.  Clearly Ladywell is going to be a better, brighter, place once the works are completed, but I urge you to do everything you can to expedite completion of this project, especially for the sake of the businesses who, if we're not careful, will be out of business before the scheme is completed so will never see the benefit - which would be cruel. Whilst I appreciate you would not normally intervene personally in matters such as this I wonder whether you'd consider, in this instance, meeting with the senior manager at Conwaysresponsible for this scheme to seek assurances in relation to early completion on-site.  The overrun of this scheme is causing a lot of bad feeling locally - which is shame as this is an excellent scheme - so LVIG urges you to do all you can to build bridges: in particular local business would, I am sure, welcome the Council's help in 're-launching' Ladywell, in the week the streetworks end, in the form of flyer, blog, twitter and website publicity so that nobody in SE13/SE4 in unaware that the brighter, better Ladywell is again "open for business".

Wednesday, February 6, 2013

Ladywell improvements - Streetworks now imminent


The Council has indicated that the streetscape work will be completed this Spring in five phases, starting at Algernon Road, then progressing into Ladywell Road east by the railway bridge then working west towards the mini-roundabout at the junction of Adelaide Avenue. The provisional schedule (which has yet to be signed-off with the contactor, London Buses and various underground service providers) is as follows - but may change during the course of the works:
1. Works at the Algernon Road (eastern) end of the scheme will start within the next week or so, probably on 11 or 18 February, with drainage works incl. the moving of gullies to new kerb alignment positions.
2. Footpath and kerbing works in Algernon Road will commence from 26 February. All property owners at 251-259 Algernon Road (incl. the Post Office and Barbers) have given permission for their forecourts to be repaved so the whole of this pavement from kerb to buildings will be one neat stretch of paving rather than the current hotch-potch. This is splendid news and will look great when completed!
3. On 1 March there will be road closure on Algernon Road to enable sewer works, and drainage works will continue to 8 March.
4. 8-26 March - lowering of Algernon Road carriageway and construction of speed tables at Gillian Street, Mercy Terrace and Algernon Road
5. 18 March - work on Ladywell Road will commence, with two way lights for the most part, but complete closure for periods of time if necessary.
For a reminder about the project see the item on the Council website.  Should you have any detailed questions/issues you can email les.senior@lewisham.gov.uk
Robert Sheppard